Changuinola I Dam, is located in district of Changuinola, in the Province of Bocas del Toro, in the western part of Panama. It is the largest roller-compacted concrete arch-gravity dam in the World.
The construction of the dam started on October 25, 2007 and its first generator was operational on November 19, 2011. The roller-compacted concrete arch-gravity dam has a maximum height of and length of . The upstream vertical face arch radius is . The induced joints are spaced at intervals, with inducers installed in every second layer after compaction. The downstream face slope varies form 0.5:1 (H:V) in the center and 0.7:1 (H:V) on the flanks.
The RCC mix strength requirements were determined by a target direct tensile strength of . The composition of the high-paste RCC mix included:
|
|